The Community Foundation for Southeast Michigan, in partnership with the US Department of Transportation, State of Michigan, City of Detroit Department of Public Works, DEGC, Eastern Market Corporation, Midtown, Inc., and the Detroit Riverfront Conservancy, will celebrate the groundbreaking of the five-phase Link Detroit greenway infrastructure project next Tuesday, Sept. 24 at 6 p.m. in Eastern Market's Lot 1 (adjacent to Shed 2).
"This goes back a few years," says Tom Woiwode, director of the Community Foundation for Southeast Michigan's GreenWays Initiative. He says that when the Dequindre Cut opened in 2009, it was always intended to run further north than where it currently ends at Gratiot. When the first portion of the Midtown Loop opened in 2010, it was intended to go further south and connect to Eastern Market. Link Detroit is the fulfillment of those intentions.
The full $25 million scope of this project is fully-funded, thanks in large part to a $10 million TIGER (Transportation Investment Generating Economic Recovery) grant in addition to support from the Community Foundation and other partners (see above).
There are five phases to this project, and most are able to operate on independent construction schedules simultaneously. Though the "ground-breaking" celebration is next Tuesday, the event is mostly ceremonial. Woiwode says they hope to already have bulldozers at work by then.
The five phases include extending the Dequindre Cut north from Gratiot to Mack, rebuilding five bridges over the Dequindre Cut's extension (with funding from the Critical Bridge Fund), extending the trail system and providing some infrastructure improvements and amenities in Eastern Market along Wilkins and Russell St., connecting Wilkins to the Midtown Loop which will be extended south along John R, and the construction of bike lanes and greenways along Dequindre Rd. north of Mack connecting the Dequindre Cut to Hamtramck. Ultimately Link Detroit will connect Midtown and Wayne State to Eastern Market to the Dequindre Cut to both Hamtramck and the Detroit River.
They hope to have construction of all five phases completed by this time next year.
Source: Tom Woiwode, director of the Community Foundation for Southeast Michigan's GreenWays Initiative